Commissioning

Commissioning will involve the sequential power on, checkout and calibration of each of the modules, starting approximately 2 days after launch:
- Inovor Apogee Platform
- ASI’s HERMES module
- Payload Management System
- THEMIS module, including simulator correlation
- Mercury module, including end-to-end comms check for all networks
- Neumann Thruster